Ocean schedule reliability falls to 27% as vessel delays average six days; plan October bookings with extra lead time

Xeneta's September data shows the fourth straight monthly drop in on-time arrivals, with Asia–North America delays near seven days and spot rates from China more than four times last year's level. Reliability should be in every 2027 carrier tender.

A harbor filled with large container cranes
A harbor filled with large container cranes. Photo: Foto K. / Unsplash

Article summary

  • Why it matters: A six-day average delay is a full week of extra safety stock, missed production windows or expedited freight. With carriers set to blank more sailings in October and contract season for 2027 approaching, procurement teams have both an operational problem now and a negotiating opportunity next.
  • What to do first: Add lead time now. Xeneta advises extra lead time for October bookings. Update planning lead times in your ERP so reorder points reflect reality.
  • Ask which services are protected. Before booking, ask carriers and forwarders which loops are least likely to be blanked.
27%
global on-time vessel arrivals in September
6.9 days
average delay, Asia to North America
$7,717/FEU
China–U.S. West Coast spot rate, early October
13%+
October capacity blanked, Far East–North America (projected)
On this page
  1. The details
  2. Reliability at a glance
  3. What six days of delay costs
  4. What procurement teams should do
  5. Updating lead times in your planning system
  6. What to put in 2027 ocean contracts
  7. What to watch next
  8. The bigger picture

The details

Xeneta’s September Schedule Reliability Scorecard shows:

  • Global on-time reliability of 27%, down 2 points and the fourth straight monthly decline. The average delay across all arrivals reached six days, up 2.4 days since the start of the second quarter. Xeneta does not expect reliability to bottom out in October.
  • Asia–North America: 20% on time, unchanged, with an average delay of 6.9 days, up 0.8 days.
  • Far East–Europe: 4% on time with a 9.9-day average delay, the worst monthly result since September 2021.
  • Carriers: Every tracked carrier posted its highest average delay of the past 12 months. Maersk was the most reliable at 47%, down from 51%. Several carriers hit 12-month lows: Hapag-Lloyd 45%, CMA CGM 30%, Cosco 18% and Yang Ming 4%. The Gemini network of Maersk and Hapag-Lloyd fell from 70% on time in June to 40% in September, and weekly data showed 28% in early October.

Causes cited include typhoons in Asia, bunker-cost pressure, strong peak-season demand and Chinese port congestion that is now causing berth delays in Europe and North America. Singapore’s average daily queue nearly doubled to 22 ships, with the average wait rising from 1.9 to 3.1 days. Shanghai’s anchorage queue shortened from 101 to 86 vessels, but waits lengthened from 1.9 to 2.7 days.

Rates remain high. The China–U.S. West Coast spot average was $7,717 per FEU in early October, more than four times the $1,778 of September 2025. Long-term rates rose 26% month over month to $3,649 per FEU as of Oct. 1. Carriers blanked 8% of planned Far East–North America capacity in September and have announced at least 13% for October, along with 17% on Far East–Europe.

Where queues are longest. Beyond Singapore and Shanghai, Xeneta’s data shows Africa as the most congested region, with 32% of vessels waiting an average of 2.5 days, while 30% of vessels in Northeast Asia waited an average of 1.6 days, according to FreightWaves. The carrier performance spread narrowed to 43 points from 45. The China–U.S. West Coast spot average of $7,717 was 8% above early September. September’s blank sailings, 6% on Far East–Europe and 8% on Far East–North America, were the third-lowest in 21 months, and planned Far East–Europe capacity for October is the highest in 22 months, leaving carriers little room to absorb delays by cancelling sailings.

Reliability at a glance

Measure September 2026
Global on-time arrivals 27%
Global average delay 6 days
Asia–North America on time 20%, with a 6.9-day average delay
Far East–Europe on time 4%, with a 9.9-day average delay
Most reliable carrier Maersk, 47%
Gemini network (Maersk and Hapag-Lloyd) 40%, down from 70% in June
Far East–North America capacity blanked 8% in September; at least 13% announced for October

Figures from Xeneta.

The gap between spot and contract. At $7,717 per FEU, the China–U.S. West Coast spot average was a little over twice the $3,649 long-term average, by our calculation, a gap of about $4,068 per container. Shippers on long-term contracts are paying much less, but only for cargo that actually moves under the contract. When sailings are blanked or cargo is rolled, the overflow often moves at spot. That makes allocation and roll protection worth nearly as much as the contract rate itself.

What six days of delay costs

A six-day average delay is not just a planning nuisance. For a business importing $10 million of goods a month by ocean, an extra six days in transit ties up roughly $2 million more in inventory at any time, by our calculation. At a 10% annual carrying cost, that is about $200,000 a year, before any stockouts, expedited freight or detention charges. Your numbers will differ, but the math is worth running before you set 2027 safety stock.

What procurement teams should do

  • Add lead time now. Xeneta advises extra lead time for October bookings. Update planning lead times in your ERP so reorder points reflect reality.
  • Ask which services are protected. Before booking, ask carriers and forwarders which loops are least likely to be blanked.
  • Put reliability in the tender. For 2027 contracts, include schedule reliability, port rotations and unscheduled calls in carrier accountability, not just rate.
  • Spread allocations. Split volume across carriers and alliances to limit exposure to a single network’s delays.
  • Review inventory policy. For critical imported parts, recalculate safety stock using current delay variability, not last year’s averages.

Updating lead times in your planning system

  1. Pull actual transit data for the past three months by lane, from booking confirmation to arrival at your facility.
  2. Use the spread, not just the average. Set safety stock on the variability you are seeing; a six-day average can hide two-week delays.
  3. Update planned lead times in your ERP or planning tool so reorder points move.
  4. Flag critical parts where a stockout stops production, and set a higher service level for them.
  5. Review monthly until reliability recovers, then step buffers back down.

This is our recommended approach.

What to put in 2027 ocean contracts

Xeneta advises shippers to make reliability, port rotations, unscheduled calls and capacity management central to carrier accountability ahead of 2027 tenders. In practice, that can mean:

  • Service commitments by string. Name the services and sailings your allocation depends on.
  • Reliability reporting. Monthly on-time data by service, not just a global figure.
  • Blank sailing rules. Notice periods and guaranteed space on the next sailing when one is cancelled.
  • Port rotation changes. Advance notice when a service drops or swaps a port that matters to you.
  • Remedies. Credits or volume flexibility when reliability falls below an agreed level.

What to watch next

  • October reliability. Xeneta does not expect reliability to bottom out in October.
  • Asian port congestion. Singapore’s queue nearly doubled to 22 ships; watch whether it clears or spreads.
  • Gemini network. Its fall from 70% to 40% on-time is worth tracking if you rely on Maersk or Hapag-Lloyd.

The bigger picture

Reliability this low has historically lasted months, not weeks. With spot rates still elevated on the trans-Pacific and falling on Asia–Europe, the 2027 tender season is a chance to trade volume commitments for service guarantees. Teams that negotiate on reliability, not just price, will carry less buffer stock next year.

Questions procurement teams are asking

How reliable are ocean carriers right now?

In September 2026, only 27% of vessels arrived on time globally, according to Xeneta, with an average delay of six days. Asia–North America on-time performance was 20%, with delays averaging 6.9 days.

What should shippers ask ocean carriers before 2027 tenders?

Which services are protected from blank sailings, how port rotations and unscheduled calls will be managed, and what accountability applies when schedule reliability falls below agreed levels.

Which ocean carrier is most reliable right now?

Maersk was the most reliable carrier in Xeneta's September scorecard at 47% on time, though that was down from 51% in August. Every tracked carrier posted its longest average delay of the past 12 months.

How reliable are container shipping schedules in 2026?

Xeneta's September 2026 scorecard showed 27% of vessels arriving on time globally, the fourth straight monthly decline, with an average delay of six days. Asia–North America was 20% on time and Far East–Europe 4%.

Which container carrier is most reliable right now?

Maersk was the most reliable carrier in Xeneta's September 2026 data at 47% on time, down from 51%. Every tracked carrier posted its highest average delay of the past 12 months.

How we reported this

This story draws on 1 source, listed below, and reflects figures as reported on October 14, 2026. The sections on why it matters and what procurement teams should do are Procurement Signal analysis. It is not legal or financial advice. See our editorial standards.

Sources

  1. FreightWaves — Shippers waiting an extra week for US-bound containers (Xeneta Schedule Reliability Scorecard)

Read more in Freight & logistics

Top 10 this week

  1. 22 products out, 100 in: the 50% Canada tariff list changes Oct. 30Tariffs & trade policy, Oct 29
  2. Boluda Shipping to buy Samskip, building a 32-vessel shortsea network from Northern Europe to West AfricaFreight & logistics, Oct 29
  3. SAP ships AI agent governance tooling: observability, an enterprise AI gateway and an EU AI Act assistantAI in procurement, Oct 29
  4. Fed holds its benchmark at 3.75–4.00% with two members dissenting for a hike; a December increase is widely expectedContracts & pricing, Oct 28
  5. IEEPA tariff refunds widen: Customs tells the trade court 'Phase 3' will open to more importers on a rolling basisTariffs & trade policy, Oct 27
  6. USPS will add a weekly fuel surcharge to parcels in January 2027, ending its no-fuel-fee advantage over FedEx and UPSFreight & logistics, Oct 26
  7. Nvidia scales AI capacity to multi-gigawatt with Oracle after locking six supplier deals, including a $1.1B U.S. testing…Semiconductors & electronics, Oct 27
  8. Wind turbines avoid Section 232 tariffs: Trump orders trade negotiations, with a report due by April 20, 2027Tariffs & trade policy, Oct 22
  9. DeepSeek banned from federal civilian procurement: the exclusion reaches products built on its modelsGovernment & public sector, Oct 20
  10. Opply raises $7.5M so AI agents can run CPG procurement end to end, joining 2026's agentic funding waveProcurement technology, Oct 21